Sand placement method using a forced dry sand placement device equipped with a bamboo net and Srew reinforced with drainage support on the pre-filled landfill
| Ministry of Land, Infrastructure and Transport New Technology No. | 390 | 
|---|
| Date of issue | July 14, 2003 | 
| Issuing agency | Minister of Land, Infrastructure and Transport, Republic of Korea | 
| Protection Period | August 6, 2003 - August 5, 2010 (7 years) | 
본문
Detail
        
        This is a method of reinforcing the dredged reclaimed ground with a 30 to 70 cm grid made of bamboo and vertical drainage supports, laying low tensile strength geotextiles, and then using a screw-equipped, forced dry sand laying device to lay sand at an even thickness.